SUMMARY OF WORK PLAN, AUG 2018 - JULY 2020 (24 MONTHS)

including project phases, work package numbers and titles, and name of lead partner.


FIRST PHASE: INITIATE & FOUND

WP 01: Start-up management. Aug 2018. Interfolk

WP 02: Methodological guide for desk research, workshops and symposium. Aug 2018. Interfolk

WP 03: Kick-off partner meeting in Copenhagen. Sept 2018. MOF

WP 04: Desk research and Survey  Compendium. Sept 2018 – Jan 2019. Culturelab

WP 05: Local idea workshops iwith Summary Reports. Sept 2018 – Jan 2019. VM

WP 06: Nordic Symposium, April 2019 in Rumšiškės. Jan – April 2019. OAM


SECOND PHASE: DEVELOP & TEST

WP 07: Second partner meeting in Rumšiškės, LT. April 2019. OAM

WP 08: Symposium Compendia, five languages PDF-ed. April – Aug 2019. Culyurelab and OAM

WP 09: Develop curricula and exemplary course packages. April - June 2019. Interfolk

WP 10: Test four national pilot courses in DK, NO, LV, LT. Sept – Oct 2019. VK and MOF

WP 11: Third 2-day partner meeting in Cesis, LV. Nov 2019. Culturelab

WP 12: Edit and publish Curricula Report, five languages PDF-ed. Oct 2019 – Feb 2020. Interfolk


THIRD PHASE: DISSEMINATE AND EXPLOITATE

WP 13: Four national 1-day conferences in DK, NO, LV, LT. Jan - April 2020. VK and OAM

WP 14: Fourth 2-day partner meeting in Leknes, Lofoten, NO. May 2020. VK

WP 15: Final dissemination and exploitation. April – July 2020. MOF


WHOLE PERIOD: TRANSVERSAL WORK

WP 16: Project website and Knowledge Portal, whole period. Aug 2018 – July 2020. MOF and Interfolk

WP 17: Dissemination ex website, whole period. Aug 2018 – July 2020. MOF

WP 18: Evaluation, whole period. Aug 2018 – July 2020. Culturelab

WP 19: Project Management, whole period . Aug 2018 – July 2020. Interfolk